Opinion of the Court.

record discloses that the Circuit Court, in rendering its opinion and judgment, speaks of the Northern Pacific Railroad Company as not having been served and as not appearing in the action. But, as was well said by the Circuit Court of Appeals, when dealing with this contention, "it cannot be said that the Northern Pacific Railroad Company was not an actual party to the litigation. It was not only made a party, but it was a proper party. It was the party in possession of the premises. sought to be recovered by the action of ejectment. At the time when the cause was removed the return of service was on file, but no default had been taken against the Northern Pacific Railroad Company, and no disposition had been made of the plaintiff's controversy against it; that defendant, in presenting its petition for removal to the Circuit Court, declared itself. to be one of the defendants to the case, and recited the fact that the cause was pending in the state court, and was properly within the jurisdiction of the Circuit Court of the United States.”

Whatever reason, therefore, the Circuit Court may have had for speaking of the Northern Pacific Railroad Company as a party not served and not appearing, it is incontrovertible, as against the record, that it was served, and whether seryed or not, it entered a general appearance by joining in the petition for removal. That it may have subsequently ceased to take an active part in the case is immaterial. The jurisdictional question must be determined by the record at the time of the transfer of the case.

Whether conflicting claims of railroad companies, under the right-of-way act of Congress, March 3, 1875, would give a Circuit Court of the United States jurisdiction independently of citizenship, under the doctrine of Doolan v. Carr, 125 U. S. 618, 620, we do not find it necessary to consider.

If, then, the case fell within the jurisdiction of the Circuit Court, we have next to inquire whether that jurisdiction was properly exercised.

The controversy was between two railroad companies, one organized under the laws of Washington Territory, the other organized under the laws of Montana Territory, and was as

Opinion of the Court.

to the right of possession of a tract of land situated in Shoshone County, in the Territory of Idaho, and over which each company claimed a right of way under the act of March 3, 1875, c. 152, 18 Stat. 482, entitled "An act granting to railroads the right of way through the public lands of the United States." This act provides that "the right of way through the public lands of the United States is hereby granted to any railroad company duly organized under the laws of any State or Territory which shall have filed with the Secretary of the Interior a copy of its articles of incorporation and due proofs of its organization under the same, to the extent of one hundred feet on each side of the central line of said road."

[ocr errors]

It was affirmatively found by the Circuit Court that the Coeur d'Alene Railway and Navigation Company, on the 6th day of July, 1886, filed its articles of incorporation in the office of the secretary of the Territory of Montana, and also filed in the office of the county clerk and recorder of the county of Lewis and Clarke, in said Territory, a certified copy of its said articles of incorporation; that the line of route of the railroad of the said company, as described in said articles of incorporation, passed over and included the land in controversy; that on the 20th day of July, 1886, the said company filed in the office of the Secretary of the Interior at Washington, D. C., a certified copy of its articles of incorporation and proofs of its organization under the laws of the Territory of Montana, which certified copy of articles of incorporation and proofs of organization were duly approved on that day by the Secretary of the Interior; that in the summer and fall of 1886 the said company constructed its railroad over said line of railroad, as described in said articles of incorporation, from the Old Mission up the main Coeur d'Alene River to the town of Kingston, and thence up the South Fork of the Coeur d'Alene River to the town of Wardner Junction, a distance of about fourteen miles; that in the month of October, 1886, the said company, for the purpose of extending its line of railroad, caused a survey to be made for its said line of railroad from said Wardner Junction up the said fork of the Coeur d'Alene River, over the

Opinion of the Court.

line described in its said articles of incorporation, through the towns of Wallace and Mullen, and marked the centre line of said road upon the ground by planting stakes at each station at one hundred feet, and at such other points as there were angles in the line, so that the line of route of said road could be readily traced upon the ground; that the said surveying and marking of said line was completed on the 31st day of October, 1886; that in making said survey the engineers of said company ran three lines through said town of Wallace, called lines " A," "B," and "C" - the two former being on the south and line "C" being on the north side of said river, the latter being the line upon which the railroad of said company was afterwards constructed, and upon the ground in controversy in this action; that in the summer and fall of 1887 the said company extended its road from the town of Wardner Junction over its line of survey, a point about one mile east of the town of Wallace, and over said line "C," the ground in controversy, through the town of Wallace, and at all times thereafter, up to and at the time of the commencement of this action, occupied and used the same as a railroad and for railroad purposes, and at the time of the commencement of this action had its roadbed, track, side tracks and depot thereon, and was using the same exclusively for railroad purposes; and that at all times above mentioned the lands in controversy, and all other lands along the line of said railroad of the Coeur d'Alene Railway and Navigation Company, as described in its articles of incorporation, were unsurveyed public lands of the United States.

If these facts stood unaffected by other evidence, the title of the Coeur d'Alene Railway and Navigation Company to the land in controversy would be clear.

It was, however, shown that on the 9th day of November, 1886, ten days after the completion of the survey of the three lines "A," "B," and "C," the said company filed in the United States land office at Coeur d'Alene, Idaho, a map or profile which was, December 3, 1886, approved by the Secretary of the Interior, and that on this map the line "B" through the town of Wallace was platted as the line of the said railroad.

Opinion of the Court.

As already stated, in the fall of 1887 the company constructed its railroad upon line "C" and across the land in controversy. But no amendment of the said map was made, nor was any approval of the Secretary of the Interior obtained to any new map covering line "C."

The plaintiff contends that the effect of the filing and approval of the map line "B" was to vest in the said company a right of way one hundred feet wide on each side of the centre line of its road, as indicated upon said map, which right could not be changed without the consent of the granting power first had and obtained. Regarding this question as one entirely between the Cœur d'Alene Railway and Navigation Company and the United States, it should be observed that the act of Congress, under which both parties claim the land in question, by its fourth section provides that, in case of unsurveyed lands of the United States, as these were, the plat need not be filed until twelve months after a survey thereof. It is, however, said that while the company might not have been required under the act to file its map at the time such filing was made, yet it had the right to do so under certain regulations of the Secretary of the Interior, in force during the period of this controversy, and that when such map was approved by the Secretary the company had secured the benefit of the act upon the line there shown, and could not thereafter alter the same. We agree with the Circuit Court of Appeals in thinking that, so far as the United States are concerned, there is nothing in the act forbidding a railroad company, having adopted one line of survey along the route provided for in its articles of incorporation, and having filed a plat thereof, to subsequently, and within the time allowed it by law for so doing, adopt another route, and that no reason is apparent why, instead of filing a second plat, it may not construct the road on the line surveyed and adopted, so long as the rights of others have not intervened. Such an actual construction and appropriation of one line would preclude the company from asserting any claim to the other lines, and hence the contention that, by running several lines through unsurveyed lands, the company sought to obtain more than the

VOL. CLX-7

Opinion of the Court.

statute gave, namely, one right of way, is met by the fact that it claimed and constructed but one line.

If the United States could not, and do not, complain, there is no foundation for the plaintiff company to do so, as it was found by the trial court that the platting of line "B," instead of line "C," was through a mistake, and that such mistake was not discovered until after the completion of the defendant's railroad and depot over and upon the ground in controversy, and that the filing of the plat showing line "B" was not done for the purpose of, in any manner, deceiving the plaintiff or any one else, and that the plaintiff was not, in any manner, misled or prejudiced by the filing of said plat or by said mistake.

Even if the Coeur d'Alene Railway and Navigation Company was duly organized as a railroad company, and, as such, was entitled to construct and maintain its road over the land in controversy, without being estopped by having filed an inaccurate map, still the plaintiff contends that the right of way in question belongs to it by virtue of a prior survey made on its behalf. The facts relevant to this contention are that the articles of incorporation, under which the plaintiff claims the land in controversy, were not filed in the office of the secretary of the Territory of Washington till the 10th day of November, 1886, and that a copy of such articles and proof of organization were not filed in the office of the Secretary of the Interior till December 22, 1886. It was, indeed, shown and found that, on October 28, 1886, W. H. Burrage, claiming to be acting for the plaintiff, surveyed a line up the Cour d'Alene River, through the town of Wallace, and over the ground in controversy, which was the line described in the articles of incorporation subsequently filed by the plaintiff company in the offices of the secretary of the Territory and of the Secretary of the Interior.

The conclusion of the courts below, on this state of facts, was that at the time of the making of said survey by W. H. Burrage over the lands in controversy, on October 28, 1886, the plaintiff was not a corporation organized for the purpose of constructing, or authorized to construct, a railroad over the